Montrose construction photos
78 photos from 9 site inspections, newest first. The percentage is how much of Montrose was built on the day of each visit.
8 April 2018100% built
4 January 201896% built
7 August 201781% built
16 March 201767% built
21 December 201656% built
7 August 201636% built
7 March 201624% built
15 November 201514% built
5 May 20159.3% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.