Oceanz 2 By Danube construction photos
42 photos from 9 site inspections, newest first. The percentage is how much of Oceanz 2 By Danube was built on the day of each visit.
25 August 202642% built
7 May 202630% built
24 December 202521% built
1 October 202515% built
16 June 202510% built
18 January 20259.6% built
8 August 20243.3% built
23 April 20240.7% built
24 October 20230% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.