36 photos from 7 site inspections, newest first. The percentage is how much of Coral Reef was built on the day of each visit.

10 August 202633% built

29 April 202627% built

8 December 202518% built

20 June 202513% built

22 January 20257.5% built

5 July 20240.7% built

20 July 20230% built

Back to Coral Reef construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.