West Avenue construction photos

62 photos from 6 site inspections, newest first. The percentage is how much of West Avenue was built on the day of each visit.

23 June 2014100% built

1 February 201477% built

23 September 201368% built

1 April 201349% built

13 December 201244% built

30 July 201230% built

Back to West Avenue construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.