93 photos from 14 site inspections, newest first. The percentage is how much of The Residences At Marina Gate 2 was built on the day of each visit.

27 May 2019100% built

10 February 201990% built

2 October 201877% built

20 June 201868% built

11 February 201855% built

29 October 201744% built

23 July 201734% built

12 April 201720% built

14 February 201718% built

16 October 201612% built

30 May 201611% built

2 February 201610% built

4 October 20159.6% built

27 May 20154.6% built