Sparkle Towers construction photos

157 photos from 16 site inspections, newest first. The percentage is how much of Sparkle Towers was built on the day of each visit.

16 June 2019100% built

12 February 201997% built

8 October 201893% built

29 May 201891% built

14 January 201890% built

19 September 201790% built

30 May 201787% built

28 December 201685% built

8 August 201680% built

13 March 201660% built

21 January 201654% built

23 November 201543% built

20 September 201533% built

23 July 201525% built

17 May 201518% built

20 November 20145.9% built

Back to Sparkle Towers construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.