Sparkle Towers construction photos
157 photos from 16 site inspections, newest first. The percentage is how much of Sparkle Towers was built on the day of each visit.
16 June 2019100% built
12 February 201997% built
8 October 201893% built
29 May 201891% built
14 January 201890% built
19 September 201790% built
30 May 201787% built
28 December 201685% built
8 August 201680% built
13 March 201660% built
21 January 201654% built
23 November 201543% built
20 September 201533% built
23 July 201525% built
17 May 201518% built
20 November 20145.9% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.