Harbour Residences construction photos
116 photos from 15 site inspections, newest first. The percentage is how much of Harbour Residences was built on the day of each visit.
18 April 2019100% built
23 July 201891% built
14 March 201885% built
22 October 201775% built
2 March 201762% built
15 November 201655% built
26 June 201640% built
16 February 201626% built
19 August 201520% built
5 May 201517% built
29 January 201515% built
13 April 201414% built
21 October 201314% built
25 February 201314% built
11 June 20121.6% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.