Continental Tower construction photos

106 photos from 10 site inspections, newest first. The percentage is how much of Continental Tower was built on the day of each visit.

8 June 2017100% built

15 January 201797% built

20 September 201695% built

2 March 201692% built

7 December 201585% built

27 August 201573% built

7 June 201564% built

3 February 201553% built

5 October 201436% built

1 April 201428% built

Back to Continental Tower construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.