The V Tower construction photos

68 photos from 7 site inspections, newest first. The percentage is how much of The V Tower was built on the day of each visit.

5 September 2023100% built

9 January 202352% built

24 August 202222% built

22 November 20214.6% built

7 July 20212.8% built

22 June 20201.2% built

8 March 20200.2% built

Back to The V Tower construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.