Cove Grand Residence By Imtiaz construction photos
22 photos from 6 site inspections, newest first. The percentage is how much of Cove Grand Residence By Imtiaz was built on the day of each visit.
8 October 202613% built
8 July 20268.7% built
29 April 20266.3% built
20 January 20265.2% built
6 October 20251.7% built
19 May 20250% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.