Verdana(Phase 2) construction photos

79 photos from 12 site inspections, newest first. The percentage is how much of Verdana(Phase 2) was built on the day of each visit.

3 June 202694% built

11 February 202691% built

20 October 202582% built

17 March 202555% built

6 November 202445% built

4 June 202424% built

26 March 202421% built

6 December 202310% built

25 September 20235.1% built

26 July 20233.7% built

2 March 20230.4% built

9 November 20220.1% built

Back to Verdana(Phase 2) construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.