Address Hillcrest construction photos
78 photos from 9 site inspections, newest first. The percentage is how much of Address Hillcrest was built on the day of each visit.
29 October 2025100% built
4 September 202598% built
13 June 202598% built
24 February 202590% built
29 August 202462% built
2 April 202450% built
25 September 202310% built
5 June 20231.3% built
30 January 20230.3% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.