Parkside Views construction photos

57 photos from 8 site inspections, newest first. The percentage is how much of Parkside Views was built on the day of each visit.

5 May 2026100% built

16 March 202694% built

4 December 202574% built

23 July 202558% built

11 April 202539% built

4 November 202422% built

13 May 20242.3% built

25 July 20230% built

Back to Parkside Views construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.