Park Heights I construction photos
118 photos from 12 site inspections, newest first. The percentage is how much of Park Heights I was built on the day of each visit.
3 September 2020100% built
5 August 202098% built
18 May 202096% built
27 January 202092% built
22 October 201981% built
27 August 201972% built
25 April 201951% built
6 January 201940% built
27 September 201823% built
11 June 201811% built
15 February 20185.1% built
7 November 20172.5% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.