Lime Gardens construction photos
62 photos from 8 site inspections, newest first. The percentage is how much of Lime Gardens was built on the day of each visit.
28 August 2025100% built
23 May 202591% built
16 January 202580% built
9 September 202461% built
25 April 202441% built
6 November 202314% built
4 July 20236.1% built
30 January 20231.3% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.