Elvira construction photos
75 photos from 11 site inspections, newest first. The percentage is how much of Elvira was built on the day of each visit.
30 June 2026100% built
4 May 202692% built
8 January 202685% built
3 September 202568% built
16 May 202557% built
21 January 202541% built
11 October 202428% built
5 March 20248.1% built
6 November 20231.5% built
14 July 20230% built
20 December 20220% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.

.jpeg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpeg&w=3840&q=75)



.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpg&w=3840&q=75)
%2520ELEVATION%252002.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
%2520Tower%252001.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
%2520ELEVATION%25201.1.jpg&w=3840&q=75)






































.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)