Dubai Hills - Hills View Community construction photos
47 photos from 9 site inspections, newest first. The percentage is how much of Dubai Hills - Hills View Community was built on the day of each visit.
28 September 2020100% built
13 May 201997% built
12 March 201892% built
19 November 201792% built
14 February 201749% built
13 October 201629% built
24 April 201623% built
23 July 201516% built
4 March 201515% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.