Dubai Hills - Hills Grove Community construction photos

49 photos from 9 site inspections, newest first. The percentage is how much of Dubai Hills - Hills Grove Community was built on the day of each visit.

28 September 2020100% built

13 May 201999% built

28 January 201897% built

19 October 201797% built

14 February 201779% built

13 October 201659% built

24 April 201634% built

23 July 201528% built

4 March 201524% built

Back to Dubai Hills - Hills Grove Community construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.