Collective 2.0 construction photos

116 photos from 11 site inspections, newest first. The percentage is how much of Collective 2.0 was built on the day of each visit.

9 February 2022100% built

13 December 202198% built

8 September 202195% built

3 June 202180% built

7 April 202171% built

22 December 202042% built

31 August 202028% built

21 May 202023% built

8 January 202017% built

11 September 20197.9% built

7 May 20192.1% built

Back to Collective 2.0 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.