Club Drive construction photos

58 photos from 9 site inspections, newest first. The percentage is how much of Club Drive was built on the day of each visit.

4 May 202675% built

13 January 202655% built

29 September 202544% built

12 July 202541% built

15 April 202527% built

26 December 202414% built

13 September 20247.0% built

16 April 20241.7% built

11 September 20230% built

Back to Club Drive construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.