Acacia At Park Heights construction photos
118 photos from 14 site inspections, newest first. The percentage is how much of Acacia At Park Heights was built on the day of each visit.
19 January 2020100% built
27 October 201998% built
27 August 201996% built
25 April 201991% built
15 January 201981% built
27 September 201871% built
28 June 201862% built
3 May 201855% built
30 January 201841% built
5 October 201723% built
17 July 201717% built
27 March 201710% built
12 December 20168.1% built
7 October 20158.0% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.