Fawad Azizi Residence construction photos

50 photos from 6 site inspections, newest first. The percentage is how much of Fawad Azizi Residence was built on the day of each visit.

2 April 2024100% built

22 August 202358% built

6 March 202321% built

4 October 20213.9% built

2 November 20201.2% built

23 January 20200.7% built

Back to Fawad Azizi Residence construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.