Farhad Azizi Residence construction photos

102 photos from 11 site inspections, newest first. The percentage is how much of Farhad Azizi Residence was built on the day of each visit.

14 July 2022100% built

25 October 202173% built

16 March 202160% built

7 October 202048% built

11 February 202033% built

6 January 202031% built

21 August 201920% built

8 July 201916% built

18 April 20198.0% built

16 January 20194.8% built

25 July 20184.8% built

Back to Farhad Azizi Residence construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.