Binghatti Avenue construction photos

56 photos from 5 site inspections, newest first. The percentage is how much of Binghatti Avenue was built on the day of each visit.

26 April 2022100% built

24 October 202175% built

28 April 202140% built

17 November 202010% built

22 March 20201.8% built