Palace Beach Residence construction photos

69 photos from 10 site inspections, newest first. The percentage is how much of Palace Beach Residence was built on the day of each visit.

15 January 2025100% built

20 August 202491% built

30 April 202474% built

25 December 202353% built

1 August 202328% built

13 April 202315% built

28 December 20227.2% built

8 September 20222.9% built

7 March 20220.6% built

15 November 20210.1% built

Back to Palace Beach Residence construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.