104 photos from 11 site inspections, newest first. The percentage is how much of The Cove Ll was built on the day of each visit.

29 April 2026100% built

26 February 202692% built

13 November 202587% built

14 August 202572% built

23 April 202562% built

20 January 202549% built

10 September 202430% built

24 April 202412% built

5 October 20233.3% built

14 June 20230.2% built

13 October 20220% built

Back to The Cove Ll construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.