Palace Residences - Dubai Creek Harbour construction photos

91 photos from 10 site inspections, newest first. The percentage is how much of Palace Residences - Dubai Creek Harbour was built on the day of each visit.

3 August 2023100% built

10 July 202397% built

25 January 202382% built

2 September 202263% built

18 March 202240% built

4 October 202120% built

5 July 202113% built

2 March 20207.1% built

12 November 20193.5% built

7 August 20190.3% built

Back to Palace Residences - Dubai Creek Harbour construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.