56 photos from 7 site inspections, newest first. The percentage is how much of Creek Beach - Grove was built on the day of each visit.

7 November 2024100% built

17 September 202495% built

7 March 202470% built

5 October 202343% built

12 June 202330% built

26 January 202311% built

13 October 20223.9% built

Back to Creek Beach - Grove construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.