17 Icon Bay construction photos

131 photos from 14 site inspections, newest first. The percentage is how much of 17 Icon Bay was built on the day of each visit.

25 August 2022100% built

27 April 202290% built

6 January 202283% built

2 September 202177% built

4 May 202170% built

22 February 202164% built

10 November 202052% built

27 July 202041% built

20 April 202031% built

5 January 202020% built

2 September 201914% built

23 May 201912% built

22 January 20194.9% built

14 August 20183.2% built

Back to 17 Icon Bay construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.