Upper Crest construction photos
94 photos from 11 site inspections, newest first. The percentage is how much of Upper Crest was built on the day of each visit.
16 November 201591% built
30 July 201580% built
21 April 201567% built
18 January 201560% built
18 November 201459% built
9 June 201441% built
17 February 201435% built
5 October 201325% built
4 June 201321% built
4 March 201315% built
25 November 201213% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.