The Address Residence - Sky View construction photos

171 photos from 17 site inspections, newest first. The percentage is how much of The Address Residence - Sky View was built on the day of each visit.

29 December 2019100% built

2 October 201994% built

29 August 201993% built

30 April 201992% built

13 January 201991% built

27 August 201885% built

25 June 201882% built

30 April 201878% built

11 January 201874% built

6 September 201768% built

5 June 201765% built

15 January 201763% built

14 June 201643% built

10 August 201525% built

25 June 20146.3% built

2 February 20142.4% built

2 October 20130.8% built

Back to The Address Residence - Sky View construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.