Rp Heights construction photos

158 photos from 17 site inspections, newest first. The percentage is how much of Rp Heights was built on the day of each visit.

31 May 2020100% built

14 May 202099% built

3 March 202098% built

10 December 201994% built

16 September 201990% built

28 May 201980% built

10 February 201971% built

31 October 201860% built

18 July 201850% built

11 March 201835% built

23 October 201730% built

7 September 201727% built

17 May 201724% built

7 December 201620% built

21 June 201610% built

2 February 20167.1% built

29 June 20153.5% built

Back to Rp Heights construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.