Forte construction photos

206 photos from 24 site inspections, newest first. The percentage is how much of Forte was built on the day of each visit.

12 September 2023100% built

19 July 202398% built

28 March 202398% built

21 February 202397% built

12 September 202292% built

20 May 202290% built

23 November 202184% built

18 August 202183% built

6 May 202180% built

26 January 202176% built

27 September 202071% built

16 June 202061% built

12 March 202054% built

24 November 201940% built

11 July 201930% built

18 February 201921% built

20 November 201818% built

12 August 201813% built

30 April 201810% built

6 February 20187.3% built

1 October 20175.6% built

12 June 20174.6% built

16 February 20172.1% built

2 November 20150% built