Dt 1 construction photos
66 photos from 7 site inspections, newest first. The percentage is how much of Dt 1 was built on the day of each visit.
16 November 2020100% built
17 September 201973% built
29 April 201951% built
20 December 201837% built
31 July 201822% built
7 March 201810% built
5 November 20176.1% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.