Burj Vista construction photos

99 photos from 12 site inspections, newest first. The percentage is how much of Burj Vista was built on the day of each visit.

12 July 2018100% built

21 March 201891% built

7 December 201788% built

20 August 201786% built

29 May 201782% built

30 April 201780% built

23 January 201771% built

5 September 201660% built

31 March 201640% built

31 August 201522% built

12 February 201519% built

22 May 20146.8% built

Back to Burj Vista construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.