Bellevue Towers construction photos
102 photos from 11 site inspections, newest first. The percentage is how much of Bellevue Towers was built on the day of each visit.
19 May 2021100% built
18 March 202199% built
12 November 202095% built
14 November 201965% built
7 July 201944% built
28 February 201935% built
28 November 201833% built
31 July 201830% built
28 February 201820% built
11 October 201712% built
12 June 20176.4% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.