Alexis Tower construction photos

137 photos from 17 site inspections, newest first. The percentage is how much of Alexis Tower was built on the day of each visit.

17 December 2024100% built

4 June 202486% built

13 March 202476% built

6 December 202371% built

31 July 202357% built

8 March 202347% built

24 November 202240% built

25 August 202236% built

18 May 202230% built

10 February 202225% built

4 January 202222% built

14 September 202120% built

13 July 202117% built

20 January 20219.3% built

24 August 20204.6% built

14 July 20202.8% built

1 October 20193.6% built

Back to Alexis Tower construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.