Damac Lagoons - Santorini (2) construction photos

79 photos from 10 site inspections, newest first. The percentage is how much of Damac Lagoons - Santorini (2) was built on the day of each visit.

9 February 2026100% built

18 June 202594% built

27 February 202588% built

10 September 202482% built

17 April 202452% built

9 October 202339% built

9 June 202323% built

3 February 20237.4% built

22 September 20223.1% built

25 May 20220.4% built

Back to Damac Lagoons - Santorini (2) construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.