Damac Lagoons - Morocco 1 construction photos

54 photos from 9 site inspections, newest first. The percentage is how much of Damac Lagoons - Morocco 1 was built on the day of each visit.

17 July 202677% built

24 March 202668% built

11 November 202554% built

10 June 202537% built

27 January 202525% built

30 September 20249.6% built

20 May 20244.3% built

7 December 20230.4% built

2 June 20230% built

Back to Damac Lagoons - Morocco 1 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.