Damac Lagoons - Costa Brava (1) construction photos

64 photos from 10 site inspections, newest first. The percentage is how much of Damac Lagoons - Costa Brava (1) was built on the day of each visit.

9 April 2026100% built

12 November 202596% built

16 June 202590% built

30 January 202578% built

13 September 202467% built

15 March 202438% built

9 October 202314% built

12 June 20234.7% built

3 February 20230.4% built

4 July 20220.1% built

Back to Damac Lagoons - Costa Brava (1) construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.