Damac Hills - Whitefield construction photos
58 photos from 8 site inspections, newest first. The percentage is how much of Damac Hills - Whitefield was built on the day of each visit.
7 December 2016100% built
22 June 201698% built
18 February 201688% built
7 September 201561% built
27 May 201547% built
21 December 201432% built
28 May 20142.5% built
6 October 20130% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.