75 photos from 11 site inspections, newest first. The percentage is how much of Damac Hills - Topanga was built on the day of each visit.

12 September 2018100% built

5 July 201899% built

14 February 201899% built

2 October 201798% built

19 June 201797% built

14 March 201793% built

20 December 201656% built

25 July 201631% built

16 March 201618% built

1 November 201514% built

13 January 20158.1% built

Back to Damac Hills - Topanga construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.