Damac Hills - The Trump Estates construction photos
76 photos from 11 site inspections, newest first. The percentage is how much of Damac Hills - The Trump Estates was built on the day of each visit.
11 April 2020100% built
17 February 202099% built
11 June 201997% built
1 April 201959% built
10 January 201918% built
15 August 201814% built
17 January 20189.3% built
8 August 201711% built
2 March 201710% built
2 November 20158.8% built
23 December 20148.8% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.