Damac Hills - The Flora construction photos
84 photos from 12 site inspections, newest first. The percentage is how much of Damac Hills - The Flora was built on the day of each visit.
25 March 2019100% built
4 October 201886% built
6 June 201884% built
17 January 201881% built
6 September 201781% built
23 May 201778% built
20 December 201672% built
1 August 201667% built
17 March 201656% built
5 October 201551% built
13 May 201543% built
23 December 201426% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.