Damac Hills - Silver Springs 3 construction photos
80 photos from 10 site inspections, newest first. The percentage is how much of Damac Hills - Silver Springs 3 was built on the day of each visit.
12 February 2025100% built
19 September 202498% built
7 May 202483% built
30 November 202368% built
21 August 202351% built
27 April 202332% built
12 December 202215% built
29 June 20223.2% built
8 February 20220.6% built
27 September 20210.5% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.



























.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)