Damac Hills-Park Residences 4 construction photos

95 photos from 13 site inspections, newest first. The percentage is how much of Damac Hills-Park Residences 4 was built on the day of each visit.

14 August 2024100% built

7 May 202494% built

30 November 202387% built

10 August 202368% built

26 May 202356% built

7 February 202343% built

13 October 202223% built

31 May 202217% built

8 February 202212% built

14 July 20219.8% built

4 February 20217.0% built

21 October 20206.2% built

12 March 20204.2% built

Back to Damac Hills-Park Residences 4 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.