Damac Hills-Park Residences 4 construction photos
95 photos from 13 site inspections, newest first. The percentage is how much of Damac Hills-Park Residences 4 was built on the day of each visit.
14 August 2024100% built
7 May 202494% built
30 November 202387% built
10 August 202368% built
26 May 202356% built
7 February 202343% built
13 October 202223% built
31 May 202217% built
8 February 202212% built
14 July 20219.8% built
4 February 20217.0% built
21 October 20206.2% built
12 March 20204.2% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.