Damac Hills-Park Residences 1 construction photos

122 photos from 14 site inspections, newest first. The percentage is how much of Damac Hills-Park Residences 1 was built on the day of each visit.

12 February 2025100% built

19 September 202495% built

7 May 202485% built

8 November 202380% built

17 July 202370% built

27 April 202360% built

8 December 202250% built

22 August 202240% built

31 May 202232% built

8 February 202226% built

14 July 202124% built

4 February 20219.8% built

21 October 20209.1% built

12 March 20206.5% built

Back to Damac Hills-Park Residences 1 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.