Damac Hills - Jasmine construction photos

66 photos from 11 site inspections, newest first. The percentage is how much of Damac Hills - Jasmine was built on the day of each visit.

11 December 2018100% built

16 July 201898% built

18 March 201894% built

15 November 201791% built

10 July 201782% built

13 April 201774% built

6 December 201653% built

1 August 201625% built

8 March 201612% built

2 November 20152.2% built

25 January 20152.2% built

Back to Damac Hills - Jasmine construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.