Damac Hills - Jasmine construction photos
66 photos from 11 site inspections, newest first. The percentage is how much of Damac Hills - Jasmine was built on the day of each visit.
11 December 2018100% built
16 July 201898% built
18 March 201894% built
15 November 201791% built
10 July 201782% built
13 April 201774% built
6 December 201653% built
1 August 201625% built
8 March 201612% built
2 November 20152.2% built
25 January 20152.2% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.