70 photos from 8 site inspections, newest first. The percentage is how much of Damac Hills - Golf Vita was built on the day of each visit.

15 March 2021100% built

7 July 202083% built

11 February 202060% built

9 September 201933% built

22 April 201912% built

28 November 20187.5% built

5 July 20186.8% built

15 February 20180.5% built

Back to Damac Hills - Golf Vita construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.