Damac Hills - Golf Greens 2 construction photos

41 photos from 7 site inspections, newest first. The percentage is how much of Damac Hills - Golf Greens 2 was built on the day of each visit.

4 September 202645% built

6 April 202628% built

9 December 202516% built

31 July 202511% built

21 January 20256.2% built

20 May 20242.0% built

25 October 20230% built

Back to Damac Hills - Golf Greens 2 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.